The Atlantic City Council, Wednesday, set February 15th as the date for a public hearing on bids to be received for several Capital Improvement Projects (CIP) valued at just over $4-million. In the plan, $3.4 million dollars will be spent on streets, while almost $634,000 is budgeted for the Parks and REC Department. The move followed a public hearing on the details of those projects, which include Hot Melt Asphalt (HMA) resurfacing on specific roads, Portland Cement Concrete (PCC) paving and Storm Sewer work, PCC patching on Linda Drive and 14th/Olive Streets, and work on the City Park sidewalk project, Phase 2. Snyder and Associates Engineer Dave Sturm ran down the list of roads residents can expect to see crews working on this Summer. The first part covered the various concrete projects.
They include: 22nd Street, from Chestnut to Palm [widening of pavement w/granular shoulder]; 1 block each of Hickory, Cedar and Locust Streets [complete reconstruction w/storm sewers added]; the addition of a storm sewer to Laural Street, from 7th to 8th; and curb and gutter work on 8th Street, between Laural and Palm. Sturm said the HMA work covers 15 sections of town, and involves minor patching, curb repairs, milling in some locations, and asphalt overlay: Birch, from 4th to 7th St.; Chestnut St., from 7th to 18th St.; 18th Street, Chestnut to Bryn Mahr; Cass Avenue; Waddell Dr.; Oak St., from 4th to 7th, and from Ridge Rd. to 21st; 17th St., from Olive to Lomas Circle, including the cul-de-sac; Mulberry St., from 9th to 10th St.; Lois Circle cul-de-sac by Redwood Dr.; Pine Street, from 3rd to 7th; 11th St., from Linn to Olive; 3rd St., from Walnut to Pine; Hazel St., from 3rd to 9th; & Elm St., from 3rd to 9th.
A storm sewer will also be added on Elm Street, near Akin Building Center. Sturm said plans for all projects should be ready to submit to contractors by sometime next week, with bids being opened on February 15th, prior to the public hearing on that date. He said the contractors for those projects will be required to begin work no later than June 1st, but regardless of when they start, there will be a deadline for completion, which by DOT standards, is no more than 50 days.
Engineer Ken Coffman, of Atlantic, talked about the projects he’s in charge of overseeing, including the milling of asphalt on 29th Street, from Highway 6 just to the west of Palm Street, and the overlaying of hot melt asphalt. His other projects include the City Park sidewalk, Phase 2, which involves the widening of the northwest spoke, from 4-to 6-feet, the replacement of the west sidewalk with a two-foot wider sidewalk, along with necessary grading, and patch work on the southwest spoke, which is already 6-feet wide. There will also be seeding done on a portion of the City Park which wasn’t done after last year’s sidewalk work was finished.
Another project, is a PCC patching project which covers 14th St. and Linda Drive, and from Olive St. to Roosevelt. Some sewer intakes in that area will also be replaced. And, PCC patch work is scheduled to take place on Olive Street, from about the KJAN studios on south, to near the north side of the Troublesome Creek bridge, as well as from just south of the bridge, to about Commerce Street. Traffic lights will be in-place once work begins to control through traffic on Olive. Work on Coffman’s portion of the CIP projects is slated to begin no later than April 2nd.
City Administrator Doug Harris said they won’t have a good idea on what the total cost of the projects will be, until the bids are received, but if there’s enough money left over from the bonding and other funds for those projects, other street repairs and/or projects that were scheduled for upcoming years, could be moved forward.