The Atlantic Parks and Recreation Department’s Board of Directors Monday evening, approved a request from Eagle Scout Grant Podhasky, for an improvement project at Sunnyside Park.
Grant Podhasky
The project involves the replacement of the fire pit on the east side of the Camblin Addition to the park. The current fire pit is falling apart and patched together with concrete blocks as support.
The current fire pit
Podhasky said when he decided to pursue the project, he looked at three options for a new fire pit. He says he considered making it into a grill, but there’s already one in the area. He also looked into fire pit kits, but they weren’t visually and functionally adequate. Another option was to use retaining wall blocks.
The option he chose was using natural limestone, set in the form of a fire ring about 24-feet in diameter. Podhasky said the pit would have a concrete base lined with pea gravel and surrounded by timbers.
The ;proposed layout of a new fire pit.
The project would use 2,000-pounds of limestone and 5.3-cubic yards of pea gravel.
Limestone blocks would serve as the basis for the fire pit.
As for seating options, Podhasky says he considered several options there, too. Split logs, wooden benches and limestone blocks were looked at, but ruled out for various reasons. The end solution was to use tree stumps, which provide a natural environment for the setting.
10 tree stumps would be placed in the circle around the fire pit. With the Park Boards’ approval, Podhasky can continue with fundraising efforts and acquire the necessary materials and equipment. Work on removing the current fire pit is expected to begin in June, with the project completed by mid-July.