Work on new Lansing bridge halted by high water

News

June 26th, 2024 by Ric Hanson

(Radio Iowa) – Work on the new Mississippi River bridge from Lansing to Desoto, Wisconsin has stopped. D-O-T engineer Clayton Burke says high water made conditions unsafe. “The contractor is completely leaving the site until the water goes back down,” he says. “There’s very little they could possibly do to overcome the water levels that we’re seeing so yeah it’ll it might be a while before you see those cranes swinging around.” Burke says Mother Nature will determine when the work gets underway again.

“We’re seeing about a week out the river gauge is going to be over 16 and a half feet. And we need that to get back down to about 12 before we can keep working on the bridge again,” Burke says. “And we’ve seen in the past when the Mississippi goes up, it goes up fast but it stays there for a long time. So we might be losing weeks to a month of scheduled time here.”

Burke says the contractor will likely bring in multiple crews once the water goes down so they can work nights and weekends to make up for lost time. The new bridge is was scheduled to be completed at the end of 2026. Burke says around 29-hundred people cross the Lansing bridge each day. The bridge that’s being replaced at Lansing was closed for a time in February after two piers shifted and they had to be repaired.