712 Digital Group - top

IUB rejects environmental survey request for Summit Carbon pipeline

Ag/Outdoor, News

October 7th, 2022 by Ric Hanson

(Radio Iowa) – The Iowa Utilities Board has denied a request for an environmental impact study for the Summit Carbon Solutions proposed pipeline. The survey request came from the Winnebago Tribe of Nebraska — but I-U-B order says it will consider specific environmental issues it has and those raised by those involved in the Summit Carbon request for the hazardous liquid pipeline permit.

The I-U-B statement says a separate environmental impact survey is not required by federal regulations for it to fulfill its statutory requirements in considering the permit. The I-U-B’s order says this was similar to a request made for to the Dakota Access Pipeline, which the board also rejected.