United Group Insurance

Hwy 6/7th Street Construction project update in Atlantic

News

August 4th, 2015 by Ric Hanson

Iowa DOT District 4 Transportation Coordinator Scott Suhr, in Atlantic, provided an update today (Tuesday), on the Highway 6/7th Street construction project. Suhr says last week, the contractor completed the taper on the west end of the project and poured two intersections and completed some sidewalk work.

Plans for this week include paving from Cherry through Plum Streets tomorrow (Wednesday), which completes the pavement for the west bound lane and turn lane. Next, the contractor will begin paving the east bound lane, starting at Plum Street. They will continue paving west until they reach the west end of the project.

They will also continue pouring driveways and intersections between mainline pours.