Highway 6/7th Street update – 5/27/15
May 27th, 2015 by Ric Hanson
Iowa Department of Transportation Planning Coordinator Scott Suhr, today (Wednesday), provided an update on the Highway 6/7th Street construction project, in Atlantic. Suhr says the contractor is milling the asphalt surface off of US 6 through Atlantic, and will be working on that for about 3 days. The schedule for the remaining of the week (weather permitted) is as follows:
- Milling the asphalt surface off of US 6
- Removal of concrete on the east end of project
- Removal at Plum Street
- Sanitary sewer at Plum Street
- Pavement removal from Plum street to 400 feet east